The recent South Australian decisions in Dexus SAHMRI2 Pty Ltd v South Australian Health and Medical Research Institute Ltd and McMahon Services Australia Pty Ltd v Minister for Infrastructure and Transport highlight the need for parties to construction contracts to pay careful attention to the drafting of dispute resolution clauses and properly consider whether the clause is fit for purpose and provides an appropriate mechanism for resolving any future disputes, prior to entering into the contract. This article provides an overview of the circumstances in which courts will enforce dispute resolution clauses, and some practical steps that parties to construction contracts can take to draft effective dispute resolution clauses.
How dispute resolution clauses are enforced by the courts
Most construction contracts contain a dispute resolution clause setting out the procedure to be followed if a dispute arises. These clauses usually provide several steps through which a dispute can be escalated: for example, a meeting between the parties’ senior leadership, prior to more formal alternative dispute resolution procedures, such as arbitration or expert determination, then finally litigation in court.
When a dispute does arise, one party sometimes commences court proceedings rather than follows the contractual dispute resolution procedure. If the other party disagrees with that course of action and wishes to comply with the contractual dispute resolution procedure, its recourse is to apply for the court proceedings to be stayed. Authorities demonstrate that the manner in which the Court will determine this application is dependent on the type of contractual dispute resolution clause under consideration.
Arbitration clauses
Arbitration clauses are governed by the national arbitration legislation: in South Australia, the relevant legislation is the Commercial Arbitration Act 2011 (SA) for domestic commercial arbitrations,[1] and the International Arbitration Act 1974 (Cth) for international commercial arbitrations.
Under the Commercial Arbitration Act 2011 (SA), if a party commences court proceedings in breach of a valid domestic commercial arbitration agreement (which includes an arbitration clause in a contract), the other party can request that the court refer the matter to arbitration. This request can be made at any time before the requesting party has submitted its ‘first statement of the substance of the dispute’, which would usually be its defence. Once a request is made, the court must refer the matter to arbitration, unless the court finds that the arbitration agreement is null and void, inoperative, or incapable of being performed.
Other dispute resolution clauses
The court has a discretion to stay proceedings commenced in breach of any non-arbitration dispute resolution clause, including clauses requiring negotiation, mediation, or expert determination.
When determining a stay application, the court’s starting point is that there is a “strong bias” in favour of holding the parties to the dispute resolution procedure they contracted for. The onus is on the party who commenced the court proceedings to establish that the dispute is not amenable to resolution by the contractual procedure, such that there is a good reason to refuse a stay.[2]
Circumstances that may favour the refusal of a stay include:
Case study 1: Dexus SAHMRI2 Pty Ltd v South Australian Health and Medical Research Institute Ltd [2025] SASC 61
This case concerned a contract for the construction of SAHMRI’s new proton therapy facility. The parties to the contract were the applicant Dexus (the owner of the facility building) and the respondents SAHMRI and ABC (a subsidiary of SAHMRI). Once construction was complete and a Certificate of Occupancy was issued, Dexus was to provide lease agreements, and SAHMRI and ABC were to return executed copies of the agreements within five business days.
After construction was complete, Dexus commenced proceedings in the Supreme Court of South Australia, claiming that SAHMRI and ABC had failed to provide executed leases as required by the contract. SAHMRI and ABC sought a stay of the proceedings, on the basis that Dexus had not referred the dispute to expert determination pursuant to the contract’s dispute resolution clause.
His Honour B Doyle J rejected the respondents’ application, declining to stay the proceedings. His Honour’s reasons for refusing a stay included:
Case study 2: McMahon Services Australia Pty Ltd v Minister for Infrastructure and Transport [2026] SASC 46
This case concerned a contract for the construction by the applicant contractor of new berthing facilities for the Kangaroo Island ferries. The contractor made several variation and delay claims against the principal.
The contractor commenced proceedings in the Supreme Court of South Australia. The principal, represented by LK Law, sought a stay of the proceedings, on the basis that the contractor had not complied with the expert determination procedure in the contract’s dispute resolution clause.
Auxiliary Justice Dart granted the stay sought by the principal. His Honour’s reasons for doing so included:
Considerations for drafting dispute resolution clauses
For contracting parties, the cases discussed above highlight the importance of giving consideration to the details of the dispute resolution clause, to ensure that it is appropriate for the types of dispute most likely to arise on the project. In particular, parties should have regard to the scale and complexities of the specific project and consider factors including:
Particularly for medium to large projects, a contracting party should seek advice on the drafting of the dispute resolution clause from a lawyer with experience in construction dispute resolution and litigation.
If you have a query about a dispute resolution clause in a contract you are negotiating, or a contract that is already on foot, please reach out to the authors to discuss.
[1] ‘Domestic commercial arbitration’ is defined in section 1(3) of the Act.
[2] See discussion in Dexus SAHMRI2 Pty Ltd v South Australian Health and Medical Research Institute Ltd [2025] SASC 61 at [18]-[22].
[3] Dexus at [26]-[27], [105]-[111], [127].
[4] Dexus at [115]-[119].
[5] Dexus at [112]-[114], [129].
[6] Dexus at [123].
[7] Dexus at [102]-[103], [125].
[8] Dexus at [130].
[9] McMahon Services at [29].
[10] McMahon Services at [25], [37].
[11] McMahon Services at [36].
[12] McMahon Services at [37].
[13] McMahon Services at [44].